The project consists of detailed engineering, procurement and implementation of all civil, mechanical, electrical and instrumentation works on a turn-key basis. The scope of the project:
- Construction of a water intake structure in a pond with 23 m dia., capacity 210.000 m3/day,
- Construction of a water treatment system, capacity 100.000 m3/day,
- Rehabilitation of sewage treatment system, capacity 136.000 m3/day, - Municipal water network distribution line, 150 km.,
- Rehabilitation of 17 sewage intermediate pump stations,
- Installation of 150.000 water meters in households.
Astana/ Kazakhstan
COMPLETION DATE: 2011