The turn-key Project consisted of the execution of all civil, mechanical and instrumentation works of two steam boilers with a capacity of 100 tons/hour steam each at a pressure of 65 bars, two turbogenerators with a capacity of 12,5 MW each and one turboblower with a capacity of 11,4 MW and the auxiliary equipment. The procurement, manuacturing and erection of equipment for the demineralization unit were also in the scope of the project.
Zonguldak/ Turkey
CAPACITY: 2x100 tons/hour steam 2x12,5 MW turbines / 11,5 MW turboblower