The turn-key project covers the construction of 49.4 km road section between km 372.6 and km 422 with the following work items:

-Site survey and mapping topographical survey

-Quarries and borrow areas.

-Earth works operations (1,010,046 m3)

-Production of Aggregate with different fractions (514,753 ton) -Screening and crushing operations.

-Base Course Pavement (93,172 m3)

-Cement of Sub-base (125,002 m3)

-Bituminous hot pavement operations (129,714 m3)

-Pipe and Box culvert (13 Pcs)

-Bridge repair and renovation works (42 m)

-Road Furniture and other miscellaneous works

Kazakhstan

COMPLETION DATE: 2014

CLIENT: Ministry of Transport and Communications Republic of Kazakhstan